2 – Roof
2.2.1 – Roof Covering
Roof Covering 1
Roof Covering 2
Roof Covering 3
DAMAGED/DETERIORATED

The roof covering material was damaged/deteriorated in some areas.  A qualified contractor should evaluate, then repair or replace as advised prior to the inspection objection deadline.

2.2.2 – Roof Covering
Roof Covering 4
Roof Covering 5
Roof Covering 6
DEGRANULATED

Some of the shingles appeared to be de-granulated in areas. A qualified contractor should evaluate, then repair or replace as advised prior to the inspection objection deadline.

2.6.1 – Flue Gas Vent Pipes
Flue Gas Vent Pipes 1
INADEQUATE CLEARANCE – ROOF

One or more combustion appliance exhaust flue(s) did not extend far enough above the roof. To ensure proper and safe operation, exhaust flues should extend at least 3 feet above the roof, and 2 feet above any portion of the roof within 10 feet (measured horizontally).  A qualified contractor should evaluate, then repair or replace as advised prior to the inspection objection deadline.

2.7.1 – Roof Drainage Systems
Roof Drainage Systems 1
BENT/DAMAGED

Gutters were bent and/or damaged at the time of the inspection.

This condition may cause problems by introducing excessive amounts of moisture to the soil beneath the foundation. Excessive moisture in the soil supporting the foundation can affect its ability to support the weight of the structure above and may cause foundation damage from soil movement. A qualified contractor should evaluate and repair or replace as necessary and according to current standards.

2.7.2 – Roof Drainage Systems
Roof Drainage Systems 2
DEBRIS IN GUTTERS

Gutters were full of debris or granules in areas and need to be cleaned. The debris in gutters can clog drainage, or be a sign gutters are sloped improperly – Either of which may cause problems by overflowing to introduce excessive amounts of moisture to the soil beneath the foundation. Excessive moisture in the soil supporting the foundation can affect its ability to support the weight of the structure above and may cause foundation damage from soil movement.

Debris in gutters can also conceal rust, deterioration, or leaks that are not visible until cleaned.

A qualified contractor should evaluate and repair or replace as necessary and according to current standards.

 3 – Attic, Insulation, and Ventilation
3.2.1 – Attic Structural Components
Attic Structural Components 1
ROOF DECKING DAMAGED/ALTERED

The roof decking had been damaged or altered. This can affect the overall structural integrity of the roof, and cause the roof to sag or fail in that area.

Trusses are specifically engineered and designed to support the roof and loads placed on it, such as snow. The individual components of a truss — webs, connectors, gusset plates, straps, clips, and fasteners — and all trusses in a roof are designed to perform together as a system. Recommend further evaluation by a licensed roofing contractor and/or structural engineer to determine the effect of the damage or alterations, and options for any necessary repairs.

3.4.1 – Insulation in Attic
Insulation in Attic 1
TOO THIN

The insulation is thinner than current thermal resistance (R-value) standards.

Recommend a qualified contractor to evaluate and repair or replace as needed.

 4 – Exterior
4.4.1 – Wall-Covering, Flashing & Trim
Wall-Covering, Flashing & Trim 1
Wall-Covering, Flashing & Trim 2
Wall-Covering, Flashing & Trim 3
DETERIORATION

The exterior wall covering is beginning to deteriorate or has deteriorated.

Recommend a qualified contractor should evaluate and repair or replace as needed.

4.4.2 – Wall-Covering, Flashing & Trim
Wall-Covering, Flashing & Trim 4
INADEQUATE GROUND CLEARANCE

The distance between the bottom of wood components and the ground surface (or grade) was not sufficient. In locations that have little or no snow, the distance should be no less than 8 inches. In locations with significant lasting snow, the bottom of wood elements should be no less than 8 inches above the average snow depth.

A qualified contractor should evaluate and repair or replace as necessary and according to current standards.

4.4.3 – Wall-Covering, Flashing & Trim
Wall-Covering, Flashing & Trim 5
SIGNS OF REPAIRS

There were signs of previously repaired damage. Recommend inquiring with current homeowners for any further information. Should repairs be significant or failing, we recommend a qualified contractor should evaluate and repair or replace as needed.

4.4.4 – Wall-Covering, Flashing & Trim
SWOLLEN – MOISTURE INTRUSION

The siding/trim had a swollen appearance due to moisture intrusion.

Recommend a qualified contractor should evaluate and repair or replace as needed.

4.5.1 – Eaves, Soffits & Fascia
Eaves, Soffits & Fascia 1
DAMAGE – EAVES

The eave(s) was damaged in one or more areas.

Recommend a qualified contractor should evaluate and repair or replace as necessary and according to current standards.

4.11.1 – Walkways
Walkways 1
HEAVING AND/OR SETTLING

The walkway(s) showed signs of heaving and/or settling in areas. Heaving is often caused by soil that has expanded in volume due to increased moisture content, or by wet soil which has expanded as it became frozen. Settlement is when the soil below a concrete slab is loose or it can no longer support the weight causing it to sink or crack.

  • This causes cracks in the concrete.
  • This creates trip hazards that could result in injury.

A qualified contractor should evaluate and repair or replace as necessary and according to current standards.

4.12.1 – Vegetation, Grading & Drainage
Vegetation, Grading & Drainage 1
TREE LIMBS CONTACT ROOF

The tree limbs that are in contact with the roof or hanging near the roof should be trimmed. Evaluating trees lies beyond the scope of the general property inspection.

Recommend a qualified contractor to evaluate and repair or replace as necessary.

4.14.1 – Exterior Faucets (Hose Bibs)
Exterior Faucets (Hose Bibs) 1
COULDN’T REMOVE THE GARDEN HOSE

The outside water faucet is connected to a garden hose. The hose could not be removed to inspect the faucet’s current operation. A qualified contractor should evaluate and repair or replace as necessary and according to current standards.

4.17.1 – Exterior Foundation Wall
Exterior Foundation Wall 1
CRACK – VERTICAL

The foundation had vertical cracks in areas. A qualified contractor should evaluate and repair as necessary before your inspection objection deadline.

4.21.1 – Roof Drainage – Downspouts & Extensions
Roof Drainage - Downspouts & Extensions 1
Roof Drainage - Downspouts & Extensions 2
Roof Drainage - Downspouts & Extensions 3
MISSING – EXTENSIONS

The downspout (s) are missing the proper 6 ft. extensions. This condition may cause problems by introducing excessive amounts of moisture to the soil beneath the foundation. A qualified contractor should evaluate and repair or replace as necessary and according to current standards.

 5 – Detached Garage
5.5.1 – Floor
Floor 1
CRACKED – SIGNIFICANT

The concrete floor in the garage was significantly cracked.  Cracks of 1/4″ or greater separation are typically indicating settlement, heaving, or structural problems. These types of cracks may present a tripping hazard. A qualified contractor should evaluate and repair as necessary.

 6 – Interior, Doors, Windows
6.2.1 – Ceilings & Walls
Ceilings & Walls 1
DAMAGED – CEILINGS

The ceilings showed signs of minor damage and wear.  A qualified contractor should evaluate and repair or replace as necessary.

6.2.2 – Ceilings & Walls
Ceilings & Walls 2
MOISTURE DAMAGE-CEILINGS

The ceilings showed evidence that moisture was entering from behind possibly including damage and deterioration.  A qualified contractor should evaluate and repair or replace as necessary.

6.4.1 – Doors
Doors 1
MISSING – FLOOR GUIDES

The door had missing or damaged floor guides.  A qualified contractor should evaluate and repair or replace as necessary.

6.5.1 – Windows
Windows 1
NO EGRESS

At the time of the inspection, the property did not have emergency escape and rescue openings that met generally-accepted current standards. Egress opening requirements:

For safety reasons, all sleeping rooms and basements greater than 200 square feet and new properties should meet the generally-accepted current standards for emergency escape and rescue openings, which include the following requirements:

1. Sill height shall not exceed 44 inches above the floor.

2. Minimum net clear opening shall be 5.7 square feet; exception – grade level windows

may have a minimum clear opening of 5 square feet.

3. Minimum net clear opening height shall be 24 inches.

4. Minimum net clear opening width shall be 20 inches.

6.8.1 – Stairways & Railings
Stairways & Railings 1
Stairways & Railings 2
MISSING – HANDRAIL

At the interior stairs, the handrail was missing.  A fall or injury could occur if not corrected. A qualified contractor should evaluate and repair or replace as necessary.

6.9.1 – Smoke & CO Detectors
CO DETECTOR MISSING

Carbon monoxide detectors were not installed within a specified distance of each room lawfully used for sleeping purposes. The inspector recommends the installation of carbon monoxide detectors in appropriate locations. Colorado House bill 1091 became effective on July 1, 2009, which requires Carbon Monoxide detectors to be installed in most properties that has a fuel-burning heater or appliance, a fireplace, or an attached garage.

There are no carbon monoxide detectors on the lower or upper levels.

 8 – Laundry
8.9.1 – Electrical Outlets
Electrical Outlets 1
GFCI PROTECTION IS NOT PRESENT

An outlet did not provide Ground Fault Circuit Interrupter (GFCI) protection. Although GFCI protection of circuits may not have been required at the time in which this home was built, safe building practices have improved with the passage of time and building standards have changed to reflect current understanding. The inspector recommends updating the existing electrical circuits to include GFCI protection. A qualified contractor should evaluate and repair or replace as necessary.

 9 – Bathroom
9.2.1 – Doors
Doors 1
LOOSE – HANDLE/KNOB

The door had a loose handle or knob.  A qualified contractor should evaluate and repair or replace as necessary.

9.5.1 – Floors
Floors 1
MISSING TRANSITION PIECE

A transition piece was missing between two sections of flooring.  A qualified contractor should evaluate and repair or replace as necessary.

9.10.1 – Drain Waste and Vent System
Drain Waste and Vent System 1
SIGNS OF REPAIR
9.13.1 – Toilets
Toilets 1
LOOSE ON THE FLOOR

The toilet was loose on the floor. This condition typically is caused by loose bolts or nuts and/or missing floor seals. Loose toilet can result in leaks, water damage, and mold, as well as damage to the toilet, water supply lines, bolts, and drainage pipes. A qualified contractor should evaluate and repair or replace as necessary.

 10 – Bathroom 2
10.5.1 – Floors
Floors 1
MISSING TRANSITION PIECE

A transition piece was missing between two sections of flooring.  A qualified contractor should evaluate and repair or replace as necessary.

10.14.1 – Tub, Shower Area
Tub, Shower Area 1
CAULK – CORNERS AND FLOOR

The tub/shower area had deteriorated or missing sealant (caulking or grout) at the corners and/or floor. Sealant is needed at wall corners inside the shower, corners from tub to wall, and along the floor perimeter.  A qualified contractor should evaluate and repair or replace as necessary.

10.14.2 – Tub, Shower Area
Tub, Shower Area 2
POSSIBLE MOLD

Evidence of a possible mold-like substance was observed bath or shower area.  We did not inspect, test, or determine if this growth is or is not a health hazard. The underlying cause is moisture. It is recommended to consult a mold inspector or mold remediation specialist to determine if further action is needed. Further analysis by a mold remediation specialist is recommended. Axium recommends our premier partner – Mold Removal Express. They can be contacted at 720-464-1555 or online at www.axiuminspections.com/mold-removal-express.

 12 – Electrical
12.2.1 – Distribution Panels
Distribution Panels 1
INADEQUATE WORKSPACE – PANEL

The distribution panel had inadequate clear space that is 3 feet deep, 30 inches wide, and 6′ 6″ in height in front of the equipment. A qualified contractor should evaluate and repair or replace as necessary.

 13 – Water Heating Equipment
13.1.1 – General Information
General Information 1
OLDER THAN 10 YEARS

The water heater was at or beyond its warranty and/or expected life expectancy.

The water heater age was determined by the photo included in this report. According to the U.S. Department of energy, these major appliances are intended to run for between 8 and 12 years. Be advised that every water heater will age differently relative to the following life span factors: water quality, mineral buildup, frequency of flushing, the volume of water utilized, size of the tank, brand, and quality of water heater. Although it was operating at the time of the inspection, the inspector can not determine the remaining life of the water heater.

13.3.1 – Pipe Connections
Pipe Connections 1
CORRODED – PIPE FITTINGS

Pipe fittings at the water heating equipment were corroded. A qualified contractor should evaluate and repair or replace as necessary and according to current standards.

13.8.1 – Temperature & Pressure Relief Valve
Temperature & Pressure Relief Valve 1
TOO SMALL, REDUCED

The TPRV pipe was too small or was reduced in size at a connection. This condition may allow a connection to burst during an emergency. A qualified contractor should evaluate and repair or replace as necessary.

 14 – Heating
14.1.1 – Heating System Information
BEYOND TYPICAL LIFE EXPECTANCY

Due to the year of manufacture, the heating system is assumed to be near the end of its expected service life. Regular maintenance and monitoring of its condition are recommended. Budgeting for repairs and future replacement is recommended. A qualified contractor should evaluate to clean, service/repair/replace as necessary, and certify the unit if possible.  InterNACHI’s Standard Estimate Life Expectancy Chart for Homes

14.5.1 – Gas Supply Shut-Off Valve
Gas Supply Shut-Off Valve 1
GAS LINE CONTACTS EXHAUST FLUE
14.6.1 – Cabinet
Cabinet 1
INADEQUATE WORKSPACE

A proper workspace platform of 30 inches by 36 inches is required in front of the cabinet. A stable pathway no less than 22 inches by 30 inches is required leading from access to the platform. An outlet and a light are required to be installed for maintenance and service personnel to work. Recommend a qualified contractor to evaluate and repair or replace as necessary.